Milestones

Year 1

No. Milestone Task Planned Delivery Delivery Report
MS1 Information Flow management tool installed 1.2 M3 01/10/2021 Report
MS2 Dissemination plan ready 1.3 M3 01/11/2021 Report
MS4 WP2 task leaders’ kick-off meeting 2.1 M2 30/06/2021 Report
MS6 Definition of CBI scheme: proposed topic and organisation at ESI 2.3 M12 02/08/2022 Report
MS7 Expert Committee set up and industrial training scheme call organised 2.4 M6 02/12/2021 Report
MS8 Industry Advisory Board launch   3.1 M6 31/10/2021 Report
MS9 I.FAST KT Report ready 3.2 M10 28/02/2022 Report
MS14 Evaluation of a CCM alternative to Molybdenum-Graphite 4.4 M16 02/08/2022 Report
MS23 Target manufacturing and characterization 6.3 M12 02/08/2022 Report
MS32 Characterization of the first length of superconductor for low losses 8.2 M6 19/01/2022 Report
MS33 Conceptual design of HTS magnet 8.3 M10 02/08/2022 Report
MS38 First seamless copper 1.3 GHz cavity produced as substrate for the coating of the SC film 9.2 M12 02/08/2022 Report
MS39 Coating facility built and tested at STFC, USI and INFN 9.3 M12 02/08/2022 Report
MS42 ARIES samples prepared for renewed SC film deposition 9.6 M6 25/11/2021 Report
MS43 Dissemination and communication plan 10.1 M12 02/08/2022 Report
MS46 Performance of Superconductive Cavities made by AM technology by Nb or Cu with Nb thin spattered film on the internal surface 10.4 M12 22/12/2023 Report
MS47 First NEG coated samples are installed on SR beamline at DLS and Soleil 10.5 M12 30/03/2022 Report
MS49 Delivery of an electro-optic waveguide prototype for demonstration at RHUL test bench 10.7 M12 02/08/2022 Report
MS50 Workshop on energy for sustainable science at research infrastructures, at ESRF 11.1 M6 31/10/2022 Report
MS55 Design review 11.2 M12 13/04/2022 Report
MS57 Projects identification for development funding 12.1 M10 09/03/2022 Report
MS63 Demonstration of operation with high efficiency and nominal power of the first GaN amplifier 13.3 M12 31/10/2022 Report

Year 2

No. Milestone Task Planned delivery Delivery Report
MS51 Workshop on Efficient RF Sources 11.1 M13 07/09/2022 Report
MS5 ACO workshop 2.2 M18  
MS10 Collection of feedback from industrial partners and RIs participating in IFAST 3.3 M20 21/03/2023 Report
MS13 First characterisation of beam windows materials under thermomechanical load and extended radiation damage 4.3 M18 16/12/2022 Report
MS15 International workshop on muon source design 5.1 M18 16/12/2023 Report
MS17 Beam requirements for dark-sector searches 5.2 M18 31/10/2022 Report
MS18 Present and future AI accelerator applications 5.2 M24 31/05/2023 Report
MS20 Engineering design of improved power supply current measurement and RF-amplifier layout 5.3 M24 31/05/2023 Report
MS21 Report on the novel accelerator landscape in Europe, facilities, projects and capabilities at the beginning of the 2020’s 6.1 M24 31/05/2023 Report
MS24 Hypothesis on the causes of the instabilities of the focal spot profile 6.4 M24 31/05/2023 Report
MS26 Magnet specifications based on optics calculations for ELETTRA. Magnetic and mechanical design including fabrication drawings 7.3 M24 07/05/2024 Report
MS28 Electromagnetic and mechanical design of the two guns 7.4 M24 21/03/2023 Report
MS30 Construction and RF tests of CompactLight accelerating structure prototype 7.5 M36
MS31 Construction readiness of combined CCT demonstrator 8.1 M20 31/10/2023 Report
MS36 HTS Nuclotron cable produced 8.6 M24 31/05/2023 Report
MS40 Construction and operation of the cavity dedicated ALD system 9.4 M24 07/10/2022 Report
MS45 Survey on current AM repair technologies for accelerator and list of possible applications 10.3 M24 31/05/2023 Report
MS48 ML model selection and implementation plan 10.6 M18 31/10/2022 Report
MS52 Workshop on efficient magnet- and RF power supplies 11.1 M22 08/08/2024 Report
MS53 Workshop on sustainable materials and lifecycle
management for accelerators
11.1 M18 21/02/2023 Report
MS59 Approval of basic engineering 12.2 M24 31/05/2023 Report
MS60 First Plasma achieved on the prototype. 12.3 M19 06/12/2023 Report
MS61 Organization of the workshop 13.1 M21 30/10/2023 Report
MS62 Central information and contact point operational  13.2 M15 02/10/2022 Report

Year 3

No. Milestone Task Planned Delivery Delivery Report
MS11 IIF Projects interim progress 4.2 M36 07/05/2024 Report
MS16 International workshop to define R&D plans 5.1 M36
MS22 LASPLA Workshop/School 6.2 M30 25/10/2023 Report
MS34 Construction of the curved formers for CCT winding 8.4 M32
MS37 International thin film workshop organization 9.1 M28 08/10/2024 Report
MS41 A facility for laser operation for complex 3D treatment is tested on 1.3 GHz cavity 9.5 M36 04/12/2024 Report
MS44 Survey on current AM applications in accelerators and expected new developments 10.2 M30 25/10/2023 Report
MS56 Magnets constructed and tested 11.3 M25

Year 4

No. Milestone Task Planned Delivery Delivery Report
MS3 Recommendations of RI-INNOV Coordination Group 1.1 M46
MS12 IIF Projects final progress 4.2 M46
MS19 Ultimate hadron-beam brightness 5.2 M48
MS25 General workshop on Task7.2 activity summary 7.2 M42 24/10/2024 Report
MS27 Prototype acceptance tests 7.3 M46
MS29 High-power test stand setup and final results of the high-power tests 7.4 M46
MS34 Construction of the curved formers for CCT winding 8.4 M32
MS35 Test of mock up coils with dummy cable 8.5 M38 16/09/2024 Report
MS54 Workshop on industrial approaches for sustainable accelerators 11.1 M42 04/03/2024 Report
MS58 Completion of strategy documents for each application area 12.1 M40 15/09/2024 Report